top of page

Naturex, Swadlincote

After an initial site visit, a plan was put in place to establish the most efficient and safest way to bring power from the canteen building over a busy traffic route, without disrupting their daily operations. 

​

  • Install temporary power to 9x portacabins

  • 6x cabins required a 63a supply to each cabin

  • 3x cabins require a 25a supply to each cabin

  • Approximately 100m of cable runs installed

  • Lock off and tag off power to the distribution board in the canteen

  • 9x individual cables will come from the new 250a distribution board in the canteen, across the road bridge to the dispatch building

  • Install cable tray down the building to the floor for cables to be laid for the cabins

  • Power up and test all work