top of page
Naturex, Swadlincote
After an initial site visit, a plan was put in place to establish the most efficient and safest way to bring power from the canteen building over a busy traffic route, without disrupting their daily operations.
​
-
Install temporary power to 9x portacabins
-
6x cabins required a 63a supply to each cabin
-
3x cabins require a 25a supply to each cabin
-
Approximately 100m of cable runs installed
-
Lock off and tag off power to the distribution board in the canteen
-
9x individual cables will come from the new 250a distribution board in the canteen, across the road bridge to the dispatch building
-
Install cable tray down the building to the floor for cables to be laid for the cabins
-
Power up and test all work